At first, the underside equipment must be installed from the corners according to the plan. The mesh should be supported over the walls which are used as columns of the slabs as thick as the concrete height, at least.
In case of fitting of meshes into the beams, the last parallel wire to the beam must be cut suitably to make the mesh be able to enter the besm. Junction of meshes to each other is performed by putting one on top of the other with the same sizes as in the plan. Binding is not necessary.

Figure 4
Placing the Wire Mesh to the Beam

As seen in figure 4. For the meshes to be placed into the beams at both sides, it is more practical to place the mesh by inserting first one side into the beam as much as possible, and than the other side by raising a little the center of the mesh.

Figure 5

After installing the underside equipment the steel shoes are faced before installing. The centers of the meshes must be seated to the top of the beams and their sparks to the steel shoes. The distance between the steel shoes is about 1-2 m. By appreciating the rest of the St 1 in the building-sites, the supporting shoes are formed by bending that steel as seen in figure 5. Binding of supporting equipments with wires is not necessary. The carrier wires supporting meshes must be on the upper layer and must be always placed vertically to the support.